Contract No. : EP/SP/52/06

Development of EcoPark in Tuen Mun Area 38

 

 
ENVIRONMENTAL MONITORING AND AUDIT

MONTHLY EM&A REPORT for

JANUARY 2008

 

 



 

 

 

 

 

 

 

 

 

Environmental Pioneers & Solutions Limited

8/F, Chaiwan Industrial Centre Building

20 Lee Chung Street, Chaiwan, Hong Kong

Tel: 2889 0569         Fax: 2856 2010

APPROVAL SHEET

 

 

DOCUMENT DATE: 31 January 2008

 

 

Prepared and Certified by: ET Leader (Environmental Pioneers & Solutions Limited)

 

 

 

Signature: _____________________      Date: __________________

           Miss Patricia Chung

 

 

 

Verified by: ____________________              Date: __________________

                        IEC

 

 

 

*        IEC ¡V Independent Environmental Checker

 

 


TABLE OF CONTENTS

EXECUTIVE SUMMARY.. 4

1.     BASIC PROJECT INFORMATION.. 6

2.     SUMMARY OF WORK ACTIVITIES AND CONSTRUCTION STATUS. 8

3.     STATUS OF ENVIRONMENTAL PROTECTION AND SITE INSPECTIONS. 10

4.     SUMMARY OF ENVIRONMENTAL PERMIT AND LICENCES. 15

5.     CUMULATIVE LOG OF COMPLAINTS AND REMEDIAL ACTION.. 16

6.     CUMULATIVE LOG OF NOTIFICATION OF SUMMONS AND PROSECUTIONS  16

7.     CONCLUSION.. 16

APPENDIX 1 - SITE LAYOUT PLAN.. 18

APPENDIX 2 - THE CONTACT PERSONS, TELEPHONE NUMBERS OF KEY PERSONNEL FOR DEVELOPMENT OF ECOPARK IN TUEN MUN AREA 38. 19

APPENDIX 3 ¡V REVISED SITE LAYOUT PLAN FOR REFUSE COLLECTION POINTS  20

APPENDIX 4 - ORIGINAL LANDFILL GAS FIELD MEASUREMENT RECORDING SHEETS  21

APPENDIX 5 ¡V CUMULATIVE LOG OF COMPLAINTS. 26

 


EXECUTIVE SUMMARY

 

This is the nineteenth monthly Environmental Monitoring and Audit (EM&A) Report for the Environmental Protection Department Contract No. EP/SP/52/06 entitled ¡§Development of EcoPark in Tuen Mun Area 38¡¨. (Environmental Permit No. EP-226/2005)

 

This report contains the results and findings of site inspection activities and EM&A works carried out by the Environmental Team (ET) of the Works Contractor as required in the contract during January 2008.

 

The site activities in the reporting period mainly consisted of landscaping works and finishing works, fitting outs and building services installation for administration building and marine frontage management office.

 

Insufficient cover to stockpile of planting soil found beside Site Office was observed. The Contractor was reminded to properly cover stockpile of planting soil with tarpaulin sheet for better dust mitigation.

 

No substantial noise impact was noted by ET during weekly environmental site walks.

 

The Contractor has used the temporary storage tank to store the effluent of aerobic wastewater treatment system and the stored effluent was pumped away regularly. As checked by the ET, there was no effluent discharge into the stormwater drain.

 

Accumulated water found in fish pond in Administration Building was removed.

 

Accumulated water found at the bottom of oil and chemical waste storage cabinet was removed.

 

Landfill gas monitoring was carried out at site; measurement results were within the Action and Limit Levels in accordance with the EM&A Manual.

 

There were no notifications of summons or successful prosecution during January 2008.

 

The planned activities for February 2008 and March 2008 with regard to development of EcoPark consist of:

 

1) Finishing Works, Fitting Outs and Building Services Installation for Administration Building and Marine Frontage Management Office

2) Landscaping Works


 

1.        BASIC PROJECT INFORMATION

 

1.1 Introduction

 

This is the nineteenth monthly Environmental Monitoring and Audit (EM&A) Report for the Environmental Protection Department Contract No. EP/SP/52/06 entitled ¡§Development of EcoPark in Tuen Mun Area 38¡¨. The site layout plan is shown in Appendix 1. The report was prepared by the Environmental Team, Environmental Pioneers & Solutions Limited, of the Works Contractor, Kaden Construction Limited. The report is to be submitted to the Works Contractor, the Engineer and the Environmental Protection Department for the project.

 

This report presents the results of the environmental monitoring of the project activities conducted during the month of January 2008. This included regular site inspections once per week for verification of implementation of the mitigation measures as recommended in the EM&A Manual and the Contractor¡¦s Environmental Management Plan (EMP).

 

Phase 1 of the construction works has already commenced in July 2006 and is anticipated to complete in April 2008.

 

The contact person and telephone number of key personnel for the captioned project are shown in Appendix 2.

 

1.2 Project Organization and Management

 

The Works Contractor has commissioned Environmental Pioneers & Solutions Limited as the Environmental Team, which comprises the environmental team leader and the environmental technicians to undertake the environmental monitoring and audit work for this project.  The project Organization Chart of Environmental Team is shown in Figure 1.1.
Figure 1.1 Organization Chart of Environmental Team

 

 

 

 

 

 

 

 

 



2.        SUMMARY OF WORK ACTIVITIES AND CONSTRUCTION STATUS

 

2.1  Works Undertaken during the Month

 

A summary of the site installation works in this month, with the information of locations, activities, equipment/materials and dates of occurrence, is provided by the Contractor, as shown in Table 2.1.

 

Table 2.1 Work Activities for January 2008

Item

Work Activities & Location

Date of Occurrence

1

Landscaping works

1 January 2008 ¡V 31 January 2008

2

Finishing works, fitting outs & building services installation for administration building & marine frontage management office

1 January 2008 ¡V 31 January 2008

 

Machineries

 

Equipment/ Plant

Quantity

1

Mobile Crane

1

2

Excavator

3

3

Generator

2

4

Air Compressor

2

5

Roller

4

6

Loader

1

7

Grab Lorry

1

8

Crane Lorry

2

9

Water Truck

1

10

Dump Truck

1

Remarks:

-         As informed by the Contractor, most equipment are mobile at site subject to work progress.

-         Refer to Appendix 1 ¡V Site layout plan for location of construction activities.

 

 

2.2 Future Key Issues

 

The Contractor has provided an updated construction program in Table 2.2 to show the planned activities for the coming three months (February 2008 ¡V April 2008). The anticipated environmental issues are summarized as follow:

 

 

 

 

Table 2.2 Construction Program and Anticipated Environmental Issues

Item

Works

Anticipated Environmental Issues

1

Finishing works, fitting outs & building services installation for administration building & marine frontage management office

-  Generation of waste from packaging materials and C&D wastes

2

Landscaping Works

-  Dust may be generated; the wheel washing should be in operation

-  Stagnant water should be removed

-  Mosquito mitigation measures should be implemented

-  Stockpiles of excavated material should be covered with tarpaulin sheet

 

The site inspection schedule for the next month (February 2008) is designated on 6, 13, 20 and 27 February 2008.

 


3.        STATUS OF ENVIRONMENTAL PROTECTION AND SITE INSPECTIONS

 

3.1 Environmental Site Inspections

 

Environmental site inspections are required to inspect the construction activities of the Development of EcoPark in order to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented.

 

Site inspections were conducted on 2, 10, 16, 23 and 29 January 2008.

 

A detailed checklist of each site inspection together with comments, relevant photos and maps have been filed and kept.

 

The findings and results of site inspections are provided in Table 3.1:

 

Table 3.1 Summary of Site Inspections

Date

Observations

Advice from ET

Outcome

Closing Date

27 December 07

Accumulated water was found at the bottom of oil and chemical waste storage cabinet

To remove accumulated water

Accumulated water was removed

02 Jan 08

16 January 08

Accumulated water was found in fish pond in Administration Building

To remove accumulated water

Accumulated water was removed

23 Jan 08

23, 29 January 08

Insufficient cover to stockpile of planting soil found beside Site Office was observed

To properly cover stockpile of planting soil with tarpaulin sheet

To be observed and inspected in the next reporting period

--

 

 

 

 

 

 

 

 

 

 

 

3.2 Air Dust

 

Excavation work at Road F near site office was finished and the site exit at Road F was closed. The site exit at Road A remained and manual wheel washing was used.

 

Insufficient cover to stockpile of planting soil found beside Site Office was observed. The Contractor was reminded to properly cover stockpile of planting soil with tarpaulin sheet for better dust mitigation.

 

3.3 Noise

 

The major noise source was vehicle movement, machinery and rock excavation in the EcoPark. Since the nearby NSRs were remote, the noise impact was minimal. There was no specific observation noted regarding noise issue. The Contractor has obtained the Construction Noise Permit on 07 August 2007.

 

3.4 Surface Water Quality

 

Since there was no water discharge at manhole, the Contractor removed the silt curtain installed at discharge point on 4 April 2007, as agreed by the Engineer¡¦s Representative. No muddy water was observed at discharge point.

 

Chemical toilets (3 nos.) have been provided by a licensed contractor, of which sewage generated is collected every three to five days without causing contamination on surface water. The Effluent Discharge Licence was issued to the Contractor on 20 November 2006.

 

The temporary storage tank was used to store the effluent of aerobic wastewater treatment system and the stored effluent was pumped away regularly. As checked by the ET, there was no effluent discharge into the stormwater drain.

 

Accumulated water was found in fish pond in Administration Building. The Contractor rectified by pumping out accumulated water.

 

 

3.5 Visual and Landscape Impact

 

Hoarding was erected at the site egress and aligned along the site boundary along Lung Mun Road. Hoardings were specially designed to be movable for future re-use in other locations.

 

During site clearance, trees were relocated to be replanted for landscaping in the future in EcoPark.

 

3.6 Waste / Chemical Waste

 

Accumulated water was found at the bottom of oil and chemical waste storage cabinet. The Contractor rectified by removing accumulated water.

 

The Contractor implemented visual inspection and distributed flyers/ notices to ensure all dump trucks have mechanical covers closed when leaving EcoPark site.

 

Separate waste collection bins were made available for collecting aluminum cans, waste paper and plastic bottles etc. The Contractor has provided the revised site layout plan for refuse collection points as shown in Appendix 3.

 

Waste dumpers were used for the collection and storage of general waste. Temporary storage areas for waste metals and waste tyres were established.

 

The Contractor has provided sufficient drip trays for all temporary electricity generators at site. These drip trays should be covered by tarpaulin sheet to minimize rainfall accumulation.

 

Excavated materials are reused as back-fill material to balance cut and fill and hence reduce the generation of materials. Surplus materials are returned to stock in centralized area with suitable protective measures. The Contractor was reminded to comply with the requirements and conditions for disposal at public fill facility and all oversized aggregates should be crushed to less than 250mm before delivering to the public fill.

 

Materials are recycled and re-used at site as much as practicable to minimize waste generation. Timbers are recycled to make temporary tools and assess ladders etc. Excavated rocks, concrete and asphalts are stored for future re-use in land formation and structural construction etc.

 

Registered waste collectors will be arranged to collect and transport the wastes whenever necessary.

 

Table 3.4 provides a summary table of waste disposal in January 2008. The Contractor has been reminded to keep good record at site in order to have a clear presentation of waste disposal.

 

Table 3.4 Summary of Waste Disposal in January 2008

Type of Waste

Disposal Site

Quantity

Remarks

General Waste

WENT Landfill

  11.87 tonnes

-

Inert C&D Material

Public Fill Facility

  101.41 tonnes

-

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.7 Landfill Gas

 

Landfill gas (LFG) monitoring was carried out on site at two (2) locations, as instructed by the Engineer¡¦s Representative. LFG measurements on 2, 10, 16, 23 and 29 January 2008 are summarized in Table 3.5, and original field measurement sheets with measurement locations are appended in Appendix 4. Measurement results are within the Action / Limit Levels in accordance with the EM&A Manual, as shown in Table 3.6.

 

Table 3.5 Summary of LFG Measurement for January 2008

 

Sampling Location

Date of Measurement

Sampling Time

Weather Condition

Methane (CH4) %LEL

Carbon Dioxide (CO2) %LEL

Oxygen (O2)

Point A

02 January 08

1505

Fine

0.0%

0.0%

20.9%

Point I

02 January 08

1510

Fine

0.0%

0.0%

20.9%

 

Point A

10 January 08

1510

Fine

0.0%

0.0%

20.9%

Point I

10 January 08

1515

Fine

0.0%

0.0%

20.9%

 

Point A

16 January 08

1620

Cloudy

0.0%

0.0%

20.9%

Point J

16 January 08

1623

Cloudy

0.0%

0.0%

20.9%

Point K

16 January 08

1625

Cloudy

0.0%

0.0%

20.9%

 

Point A

23 January 08

1530

Fine

0.0%

0.0%

20.9%

Point J

23 January 08

1534

Fine

0.0%

0.0%

20.9%

Point K

23 January 08

1538

Fine

0.0%

0.0%

20.9%

 

Point A

29 January 08

1428

Cloudy

0.0%

0.0%

20.9%

Point J

29 January 08

1431

Cloudy

0.0%

0.0%

20.9%

Point K

29 January 08

1435

Cloudy

0.0%

0.0%

20.9%

 

Remarks:

1)       As agreed by the Engineer¡¦s Representative, the landfill gas measurements on January 2008 were carried out with two instruments : one for the measurements of methane and carbon dioxide, another for the measurement of oxygen.

2)       As agreed by the Engineer¡¦s Representative, the number of locations of landfill gas measurement was changed to three, started from 16 January 2008.

 

 

 

 

 

 

 

 

Table 3.6 Action Levels, Limit Levels and Event and Action Plan for LFG (From EM&A Manual)

Parameter

Level

Action

Oxygen

Action Level  < 19% O2

Ventilate trench/ void to restore O2 to > 19%

Limit Level   < 18% O2

Stop works

Evacuate personnel/prohibit entry

Increase ventilation to restore O2 to > 19%

Methane (CH4)

Action Level  >10% LEL

Post ¡§No Smoking¡¨ signs

Prohibit hot works

Increase ventilation to restore CH4 to <10% LEL

Limit Level  >20% LEL

Stop works

Evacuate personnel/prohibit entry

Increase ventilation to restore CH4 to <10% LEL

Carbon Dioxide (CO2)

 

Action Level  >0.5% CO2

 

Ventilate to restore CO2 to < 0.5%

Limit Level  >1.5% CO2

Stop works

Evacuate personnel/prohibit entry

Increase ventilation to restore CO2 to < 0.5%

 

 

4.        SUMMARY OF ENVIRONMENTAL PERMIT AND LICENCES

 

ET has checked with the Contractor for the status of all environmental permits and licenses for this project as at January 2008, which is summarized in Table 4.1. ET will follow the application process of the outstanding permits / licenses and will provide suitable assistance whenever appropriate.

 

Table 4.1 Summary of Environmental Permits/ Licences

Description

License / Permit No.#

Date of Issue

Date of Expiry

Status/Remarks

Environmental Permit

EP-226/2005

9-Sept-2005

--

Issued

Registration of Waste Producer

5111-421-K2869-02

27-Jul-2006

--

Issued

Construction Noise Permit

GW-RW0402-07

07-Aug-2007

28-Feb-2008

Issued

Effluent Discharge Licence

EP760/421/011762/I

20-Nov-2006

1-Dec-2011

Issued

 

 

5.        CUMULATIVE LOG OF COMPLAINTS AND REMEDIAL ACTION

 

The cumulative log of complaints is referred in Appendix 5.

 

6.        CUMULATIVE LOG OF NOTIFICATION OF SUMMONS AND PROSECUTIONS

 

No notification of summons and no prosecutions occurred during January 2008.

 

7.        CONCLUSION

 

There is no summon nor prosecutions reported during January 2008.

 

Insufficient cover to stockpile of planting soil found beside Site Office was observed. The Contractor was reminded to properly cover stockpile of planting soil with tarpaulin sheet for better dust mitigation.

 

Effluent of aerobic wastewater treatment system was temporarily stored in the storage tank and pumped away. As checked by the ET, there was no effluent discharge into the stormwater drain.

 

Accumulated water was found in fish pond in Administration Building. The Contractor rectified by pumping out accumulated water.

 

Accumulated water was found at the bottom of oil and chemical waste storage cabinet. The Contractor rectified by removing accumulated water.

 

The Contractor has been using the waste management and record system including allocation of waste storage areas and the trip ticket system as proposed in the Environmental Management Plan.

 

In addition to the daily landfill gas monitoring carried out by the Contractor on site,  weekly landfill gas monitoring was also carried out by the ET on site. The measurement results from ET shown in Table 3.5 were within Action and Limit levels in accordance with EM&A Manual.

 

The Contractor was advised to pay more efforts on environmental concerns and awareness such as site tidiness and mosquito hazard from stagnant water at site.


APPENDIX 1 - SITE LAYOUT PLAN

 

 

ª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Tenant Lot T7ª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Oil and Chemical Waste Storage Areaª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Road Fª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Road Dª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Marine Front Management Office ª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Road Cª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Site Entrance at Road Aª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Administrative Building ª½½u¹Ï»¡ 2 (¥[¤W±j½Õ½u): Road A¤å¦r¤è¶ô: EcoPark Phase 2


APPENDIX 2 - THE CONTACT PERSONS, TELEPHONE NUMBERS OF KEY PERSONNEL FOR DEVELOPMENT OF ECOPARK IN TUEN MUN AREA 38

 

 

Company/Department

Name

Position

Telephone

Scott Wilson Ltd.

Mike Bains

Independent Environmental Checker

--

Scott Wilson Ltd.

Mr. Michael Lo

Senior Resident Engineer

6290 8860

Scott Wilson Ltd.

Mr. Andy Cheung

Resident Engineer

6111 9703

Scott Wilson Ltd.

Mr. C S Lam

Senior Inspector of Works

9861 8011

Kaden Construction Limited

Mr. K M Book

Project

Manager

9193 8680

Kaden Construction Limited

Mr. Stephen Leung

Section Agent

9071 7657

Environmental Pioneers & Solutions Limited

Miss. Patricia Chung

Environmental Team Leader

2185 0123

Environmental Pioneers & Solutions Limited

Mr. Harvey Yung

Environmental Technician

2185 0172

Environmental Pioneers & Solutions Limited

Mr. Lam Ho Chun

Environmental Technician

2185 0154

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


APPENDIX 3 ¡V REVISED SITE LAYOUT PLAN FOR REFUSE COLLECTION POINTS


APPENDIX 4 - ORIGINAL LANDFILL GAS FIELD MEASUREMENT RECORDING SHEETS

 

 

 


 

 


 

 

 

 

 

 

 

 

 

 


 

APPENDIX 5 ¡V CUMULATIVE LOG OF COMPLAINTS

 

CUMULATIVE LOG OF COMPLAINTS

Environmental Parameters

No. of Outstanding Complaints

No. of complaints received in January 2008

Cumulative no. of complaints received since the commencement of project

Air

0

0

2

Noise

0

0

0

Water

0

0

0

Waste

0

0

0

Total

0

0

2

 

DETAILS OF COMPLAINTS AND REMEDIAL ACTIONS

Log Ref.

Date of Compliant received

Location

Complainant

/Date

Details of Complaint

Investigation

/Mitigation Action

Investigated by/ Date

-

-

-

-

-

-

-